5 October 2026 – DG TAXUD reports that the 50 tonne CBAM threshold remains below the one per cent limit. The assessment comes 153 days late, without a report, methodology or data. A new factsheet now also explains CBAM certificates, but the rules are still missing: neither the legal act governing certificate sales nor the rules for crediting carbon costs paid in the country of origin have yet been adopted.
CBAM De Minimis Threshold: Brussels Reviews Too Late and Without Evidence
The Directorate General for Taxation and Customs Union, DG TAXUD, estimates just one minute of reading time for its notice of 30 September. It contains a single result: between April 2025 and March 2026, the 50 tonne threshold exempted 0.87 per cent of embedded emissions from CBAM obligations. The statutory ceiling of one per cent, it says, was respected.
153 Days Late
The CBAM Regulation requires the Commission to carry out this assessment by 30 April 2026. It delivered on 30 September. That is 153 days late for a deadline Brussels set itself. The same authority demands day precise compliance from importers, under threat of penalties.
No Data, No Methodology
More serious than the delay is what is missing. No report, no methodology note, no dataset. Neither the notice nor DG TAXUD’s CBAM pages contain a working paper.
Which emissions values were used and how many importers the data cover remains unclear. The legally decisive figure is also missing: the threshold calculated under Annex VII. Only that determines whether the Commission must act by delegated act.
One Number Is Not an Assessment
For around nine out of ten importers, the threshold is not a footnote but the dividing line between exemption and substantial additional costs. Anyone responsible for monitoring it must disclose the calculation. A number without an explanation is not an assessment. It is a claim.
CBAM Certificates: Brussels Delivers a Factsheet Instead of Regulations
On 30 September, DG TAXUD explained how CBAM certificates work. The factsheet summarises what is already set out in the Regulation. What importers actually need is still missing: the delegated act on sales, repurchase and fees. It had been planned for the second quarter and is now expected in the fourth. Sales are due to start on 1 February 2027. As Parliament and Council may have up to four months to object, there is a risk that the system will start without a completed rulebook.
Third Country Carbon Price: Draft Pending for Five Months
The industry has been waiting even longer for the implementing regulation under Article 9. It is supposed to determine how carbon prices paid in the country of production are credited. It was meant to be completed in the first quarter of 2026. Since 13 May, only a draft has been available. There is no evidence that Member States have voted on it.
Obstacles by Design
Our assumption is that the delay is no coincidence. The draft already caps climate related credits at ten per cent and makes recognition conditional on certified evidence. The end result is likely to be a rulebook that neither a third country nor the declarant can realistically satisfy.
This Is Not Legal Certainty
Nine months into the definitive phase, both core elements of the payment side are still missing. Companies are supposed to calculate their costs. Brussels hands out brochures as placebos instead.
Latest news
- New CBAM Study: Relief from 2028, but Not for SMEs
- Stainless Steel Trade Defence: Five EU Proceedings, Two Speeds?
- EU Steel Regulation: New Consultation in a Whisper
We at the Gerber Group have been trading in stainless steel worldwide for over 20 years. We are your experts when it comes to purchasing, import, logistics and services. Information is a vital part of this. Because only then can you and we make the right decisions. Do you have any questions? Contact us now.